Hi all,
We have a small installation of 42 cameras. Usually our installations are bigger and we separate the management server from the recording server. However, due to the small installation, we want to do a single installation and install everything on the same server.
However, I don't see this option on the Milestone server calculator, and now we are not sure which hardware to use.
I know it should not be too demanding, as it only 42 cameras at 4CIF. Milestone calculator says we should use Xeon E5-2603 V4 for the recording server, and we wonder if the addition of the Management server in the same box will require us to change the hardware.
Any advice from your experience will be greatly appreciated.